MoDOT to begin work on lengthy resurfacing project

construction guy

MEADVILLE, Mo. - A resurfacing project in Livingston County is set to begin next Monday.

The Missouri Department of Transportation says crews with Herzog Contracting Corporation will be working on U.S. Route 36 from eastbound Route C to Parson's Creek, just over the Linn County line, and westbound from Parson's Creek to Coon Creek.

Repairs will start next week with roadside work and guardrail work scheduled to begin next month. Pavement repairs will start in late August with resurfacing beginning in September. Crews expect to wrap up work by the end of October.