July 25, 2023Maryville, Mo. | By: Jeremy Werner
MARYVILLE, Mo. - With mill and overlay complete, the first phase of the South Main Corridor project in Maryville is nearly complete.
At Monday night's brief city council meeting, City Manager Greg McDanel gave an update on progress.
Crews won't lay down new grass until September. As for what comes next in the overall project, construction bids are still out for phase two of the project.