St. Joseph, Mo. – The following is a list of general highway maintenance and construction work the Missouri Department of Transportation has planned in the Northwest Missouri region for the week of Dec. 2-8.

There also may be moving operations throughout the region, in addition to the work mentioned below. Inclement weather may cause schedule changes in some of the planned work. Check the MoDOT Traveler Information Map at http://traveler.modot.org, or download the app for updated information.

MoDOT asks drivers to work with us by buckling up, putting your phone down, slowing down and moving over in work zones.

Atchison County

Route N – Pothole patching from U.S. Route 136 to the Holt County line, Dec. 2-6.

Route 46 – Pothole patching from U.S. Route 59 to Route EE, Dec. 2-6.

Caldwell County

Route D – CLOSED until further notice at the Shoal Creek Bridge due to deck deterioration. This bridge is currently scheduled for the January 2025 contractor letting through the Statewide Transportation Improvement Program. https://www.modot.org/route-d-bridge-replacement-caldwell

Chariton County

Route 11 – CLOSED at the Salt Creek Bridge for a bridge replacement project through March 2025. (Capital-Horner & Shifrin). *1

Route ZZ – CLOSED for a culvert replacement from Parish Road to Pedan Chappel Road, Dec. 3-4, 8 a.m. to 3 p.m. daily.

Route W – CLOSED for a culvert replacement from Route 129 to Prairie Valley Avenue, Dec. 2, 7 a.m. to 3 p.m.

Route KK – Bridge maintenance at the Little Chariton River Bridge, Dec. 2-3. The bridge will be narrowed to one lane around-the-clock with temporary traffic signals and a 12 foot with restriction.

Route UU – CLOSED for a culvert replacement from Route 5 to Dooley Ford Road, Dec. 3, 7 a.m. to 3 p.m.

Route UU – CLOSED for a culvert replacement from O Bryan Avenue to Dooley Ford Road, Dec. 4, 7 a.m. to 3 p.m.

Daviess County

Route B – CLOSED for a culvert replacement from Route 13 to Route UU, Dec. 3-5, 8 a.m. to 3 p.m. daily.

Route B – CLOSED for a culvert replacement from Route 13 to 207 Street, Dec. 3-4, 8 a.m. to 3 p.m. daily.

Holt County

Lincoln Road – CLOSED for a culvert replacement from Route E to 220 Road, Dec. 2, 7 a.m. to 3:30 p.m.

I-29 – Concrete replacement northbound driving lane from 80.0 mile marker to 80.6 mile marker, Dec. 2-3.

Nodaway County

Route NN – CLOSED until further notice at the Platte River Bridge west of Parnell due to significant bridge deterioration. This bridge is currently scheduled for the March 2025 contractor letting through the Statewide Transportation Improvement Program.

U.S. Route 136 – Shoulder work from Birch Road to Apollo Trail, Dec. 3.

U.S. Route 71 – Shoulder work from U.S. Route 136 to Route FF, Dec. 4.

Putnam County

Route 129 – CLOSED at the North Blackbird Creek Bridge for a bridge rehabilitation project through February 2025. (Capital-Horner & Shifrin). *1

Route M – CLOSED at the Medicine Creek Fork Bridge for a bridge rehabilitation project through January 2025. (Capital-Horner & Shifrin). *1

 

---

*1 This bridge is part of the NWBB (Northwest Bridge Bundle) program. The design-build team is Capital-Horner &Shifrin. More info: NWBB program web page.

###